Loggers Way Sewer Replacement Project - for Residents who live on Loggers Way from Kinburn Side Road
Do you live within the project scope? Please refer to the below 5 Ws:
What: Sewer Replacement - Project scope covers 293m
Why: To address structural deficiencies
When: April 18, 2022 – June 10, 2022
Where: Loggers Way from Kinburn Side Road to Early Avenue
Who: Main Contractor - Core Civil Construction Sub-Contractor - Englobe (for pre-construction inspections)
Traffic Impacts: A road closure will be in place for the duration of the project. Residents, businesses and emergency services will have full access.
Please note: If your property is located within the project scope, you have received a Pre-Construction Survey Notice. This pre-construction inspection is 100% voluntary. Its purpose is to document the existing condition of your home to get a baseline condition inspection prior to construction. Any potential or realized claims for damage go through the contractors, who are all insured against damages. Should you decide to not participate in this pre-construction inspection, you may have difficulties proving your claim and case to the contractors.